Tribunals · Hertsmere Borough Council · 2017 rating list

Sky Studios Elstree, Rowley Lane, WD6 1FX

Film studios and premises Decided 7 October 2025 CHG101186430 WSP

OutcomeDismissedThe appeal failed, leaving the value at the figure the Valuation Officer had already conceded.
Original RV · 2017 list£3,180,000
Ratepayer sought£2,860,000
VO conceded first£2,940,000−8% before the hearing
Tribunal decided£2,940,000from 20 Feb 2023

Figures are as stated in the decision, and are values in the 2017 list; a dash means the document does not state that figure. This judgement decided 5 properties together; the figures above are for this appeal's property (SKY STUDIOS ELSTREE, ROWLEY LANE, BOREHAMWOOD, HERTS WD6 1FX). Every property is listed below.

The 5 properties in this decision

One judgement covered all of these appeals. Each property’s figures as the judgement states them (2017 list); this appeal’s property is highlighted.

The properties covered by this tribunal decision, with the figures it states for each
PropertyOriginal RVSoughtTribunal decidedOutcome
SKY STUDIOS ELSTREE, ROWLEY LANE, BOREHAMWOOD, HERTS WD6 1FX£915,000£555,000£640,000Allowed in part
SKY STUDIOS ELSTREE, ROWLEY LANE, BOREHAMWOOD, HERTS WD6 1FX£1,490,000£1,190,000£1,190,000Allowed
SKY STUDIOS ELSTREE, ROWLEY LANE, BOREHAMWOOD, HERTS WD6 1FX£2,580,000£2,190,000£2,190,000Allowed
SKY STUDIOS ELSTREE, ROWLEY LANE, BOREHAMWOOD, HERTS WD6 1FX£2,880,000—£2,600,000Dismissed
SKY STUDIOS ELSTREE, ROWLEY LANE, BOREHAMWOOD, HERTS WD6 1FXThis appeal£3,180,000£2,860,000£2,940,000Dismissed

What was argued and what the tribunal found

Sky UK Limited challenged the rateable values of a newly constructed film studio complex across five phases, arguing that disturbances from ongoing construction works throughout the completion period should result in higher allowances than those proposed by the Valuation Officer. The tribunal accepted that a tapered approach to allowances was appropriate, as the film studio use was more severely impacted by construction work than typical industrial premises. The tribunal allowed three appeals in part or in full (phases 1-3), allowing allowances of 30%, 20%, and 15% respectively, while dismissing two appeals where it found the VO's allowances of 10% and 7.5% for phases 4-5 to be fair and reasonable given the proximity to completion.

Summary generated from the decision text and checked against it. The appellant was Sky UK Limited, represented.

Grounds argued

  • Building works or disturbance nearby
Change of circumstances
construction works
Evidence
Photographs, Expert report
Hearing
22 September 2025

Similar decisions

All decisions in Hertsmere Borough Council ·

Is your own rateable value in line?

A free check compares a property with the assessments around it and says plainly whether there is anything worth pursuing.

Check a property

The tribunal’s decision in full

Download the PDF · Find it on valuationtribunal.gov.uk

Decision © Crown copyright, published by the Valuation Tribunal Service under the Open Government Licence v3.0 and reproduced unaltered. This site does not index the names of private individuals that appear in decisions. Information, not advice.