What was argued and what the tribunal found
The appellant contended that the completion date of 8 June 2024 was too soon, arguing that real-life logistical constraints on fitting out multiple floors simultaneously should extend the period to 19 July 2025. The tribunal found that such scheduling constraints were merely preparatory works before commencement of works on each individual floor, not incidental works that could prolong completion periods under Schedule 4A paragraph 9. The tribunal therefore dismissed the appeals, confirming that 8 June 2024 was a reasonable deemed completion date, being 11.5 months after practical completion on 19 June 2023, with fit-out taking 16-20 weeks per floor.
Summary generated from the decision text and checked against it. The appellant was MEC LONDON PROPERTY 2 (NOMINEE 1) LIMITED & MEC LONDON PROPERTY 2 (NOMINEE 2) LIMITED, represented.
Grounds argued
- Effective date
- Evidence
- Expert report
- Cases cited
- London Merchant Securities plc v Islington LBC [1987] 1 AC 303; JLG Investments Ltd v Sandwell District Council (1977) 20 RRC 61; English Cities Fund v Standard Life [2013] RA 215; Newham LBC v Rad Phase 1 Type B Property Co No 1 Limited [2020] RA 384; Delph Property Group Ltd v Alexander (VO) [2019] RA 233; Porter v Gladman [2011] UKLC 204; Hermes Property Unit Trust v Roberts (VO) [2021] UKUT 308(LC); Graylaw Investments Ltd v Ipswich BC [1979] RA 111
- Hearing
- 21 October 2024
Similar decisions
- 5 TH FLR 1, BARTHOLOMEW LANE, EC2N 2AX — Dismissed, 10 Sept 2026
- Petronas Energy Trading Ltd, Petronas Energy Trading Ltd, EC4M 7AW — Dismissed, 20 Jul 2026
- Equistone Partners Europe Limited, PT 6TH FLR 60 Ludgate Hill, EC4M 7AW — Dismissed, 20 Jul 2026
- Ropes & Gray International Llp, 5th Floor South, EC4M 7AW — Dismissed, 20 Jul 2026
All decisions in City of London Corporation · Offices nationally
Is your own rateable value in line?
A free check compares a property with the assessments around it and says plainly whether there is anything worth pursuing.
Check a propertyThe tribunal’s decision in full
Decision © Crown copyright, published by the Valuation Tribunal Service under the Open Government Licence v3.0 and reproduced unaltered. This site does not index the names of private individuals that appear in decisions. Information, not advice.