Tribunals · Hertsmere Borough Council · 2017 rating list

Sky Studios Elstree, Rowley Lane, WD6 1FX

Film studios and premises Decided 7 October 2025 CHG101192058 WSP

OutcomeAllowedThe tribunal reduced the rateable value.
Original RV · 2017 list£2,580,000
Ratepayer sought£2,190,000
VO conceded first£2,320,000−10% before the hearing
Tribunal decided£2,190,000from 19 Dec 2022

Figures are as stated in the decision, and are values in the 2017 list; a dash means the document does not state that figure. This judgement decided 5 properties together; the figures above are for this appeal's property (SKY STUDIOS ELSTREE, ROWLEY LANE, BOREHAMWOOD, HERTS WD6 1FX). Every property is listed below.

The 5 properties in this decision

One judgement covered all of these appeals. Each property’s figures as the judgement states them (2017 list); this appeal’s property is highlighted.

The properties covered by this tribunal decision, with the figures it states for each
PropertyOriginal RVSoughtTribunal decidedOutcome
SKY STUDIOS ELSTREE, ROWLEY LANE, BOREHAMWOOD, HERTS WD6 1FX£915,000£555,000£640,000Allowed in part
SKY STUDIOS ELSTREE, ROWLEY LANE, BOREHAMWOOD, HERTS WD6 1FX£1,490,000£1,190,000£1,190,000Allowed
SKY STUDIOS ELSTREE, ROWLEY LANE, BOREHAMWOOD, HERTS WD6 1FXThis appeal£2,580,000£2,190,000£2,190,000Allowed
SKY STUDIOS ELSTREE, ROWLEY LANE, BOREHAMWOOD, HERTS WD6 1FX£2,880,000—£2,600,000Dismissed
SKY STUDIOS ELSTREE, ROWLEY LANE, BOREHAMWOOD, HERTS WD6 1FX£3,180,000£2,860,000£2,940,000Dismissed

What was argued and what the tribunal found

The appellant (Sky Studios) challenged the rateable values for five phases of a new film studio, arguing that substantial allowances should be made for disturbances caused by ongoing construction works affecting site security, power/lighting, access, and noise/dust/vibration. The tribunal, having inspected the property and reviewed photographs showing significant construction activity, found that a tapered allowance approach was appropriate, with the impact diminishing as construction progressed. The tribunal allowed appeals 1-3 in part or fully, awarding allowances of 30%, 20%, and 15% respectively, but dismissed appeals 4-5 as the agreed allowances of 10% and 7.5% were reasonable given proximity to completion.

Summary generated from the decision text and checked against it. The appellant was SKY UK LIMITED, represented.

Grounds argued

  • Building works or disturbance nearby
Change of circumstances
construction works
Evidence
Photographs, Expert report
Hearing
22 September 2025

Similar decisions

All decisions in Hertsmere Borough Council · Pubs, hotels and leisure nationally

Is your own rateable value in line?

A free check compares a property with the assessments around it and says plainly whether there is anything worth pursuing.

Check a property

The tribunal’s decision in full

Download the PDF · Find it on valuationtribunal.gov.uk

Decision © Crown copyright, published by the Valuation Tribunal Service under the Open Government Licence v3.0 and reproduced unaltered. This site does not index the names of private individuals that appear in decisions. Information, not advice.