Tribunals · West Oxfordshire District Council

Unit 1 D H Engineering, North Leigh Business Park, OX29 6SN

Industrial unit Decided 3 June 2021 VT00006854

OutcomeDismissedThe appeal failed and the rateable value was left unchanged.
Original RV—
Ratepayer sought—
VO conceded first—
Tribunal decided—from 25 Nov 2019

Figures are as stated in the decision; a dash means the document does not state that figure. This decision covers 2 properties; the figures shown are for the first listed.

What was argued and what the tribunal found

The appellant contested the completion date of 25 November 2019 set by the billing authority for two newly built industrial units, arguing that substantial outstanding works remained including incomplete access roads, missing internal fixtures, and unfinished utility connections. The tribunal found that the billing authority's two-week timeframe was reasonable for completion of the non-essential internal items, and that no compelling evidence demonstrated the works could not have been completed within that period, dismissing the appeals.

Summary generated from the decision text and checked against it. The appellant was D H Building Services, represented.

Grounds argued

  • Other
Evidence
None from the ratepayer
Hearing
26 May 2021

Similar decisions

All decisions in West Oxfordshire District Council · Industrial and warehouses nationally

Is your own rateable value in line?

A free check compares a property with the assessments around it and says plainly whether there is anything worth pursuing.

Check a property

The tribunal’s decision in full

Download the PDF · Find it on valuationtribunal.gov.uk

Decision © Crown copyright, published by the Valuation Tribunal Service under the Open Government Licence v3.0 and reproduced unaltered. This site does not index the names of private individuals that appear in decisions. Information, not advice.