Commercial units Decided 24 April 2025 VT00026730

OutcomeDismissedThe appeal failed and the rateable value was left unchanged.
Original RV—
Ratepayer sought—
VO conceded first—
Tribunal decided—from 11 Oct 2024

Figures are as stated in the decision; a dash means the document does not state that figure. This decision covers 6 properties; the figures shown are for the first listed.

What was argued and what the tribunal found

The appellant company contended that six commercial units at Town Road had not reached completion by 11 October 2024, citing outstanding works including unconnected utilities, unfinished communal areas, and delays in planning restrictions. The tribunal found the units were substantially complete with only minor cosmetic works and utilities remaining, and applying the principle that delays in obtaining approvals should be excluded, considered it reasonable that connection could be completed within one day. The appeals were dismissed.

Summary generated from the decision text and checked against it. The appellant was Mahwan Properties Ltd, represented.

Grounds argued

  • Validity of the proposal · decisive
Evidence
Photographs
Cases cited
London Merchant Securities plc and Trendworthy Two Ltd v. Islington London Borough Council
Hearing
25 March 2025

Similar decisions

All decisions in Stoke-on-Trent City Council ·

Is your own rateable value in line?

A free check compares a property with the assessments around it and says plainly whether there is anything worth pursuing.

Check a property

The tribunal’s decision in full

Download the PDF · Find it on valuationtribunal.gov.uk

Decision © Crown copyright, published by the Valuation Tribunal Service under the Open Government Licence v3.0 and reproduced unaltered. This site does not index the names of private individuals that appear in decisions. Information, not advice.